Who wins, who pays, part 9

Passed is not switched on: which of Canada's fast-track laws are actually in use

Since the US tariffs, Canada's governments have passed laws to approve projects faster. Three of the seven we follow are in use. The busiest is the narrowest; the broad powers to set other laws aside mostly sit idle.

By W.F.Published Updated 24 min readSources and method

Updated since publication: 1 correction, 1 update

Also in French: Adoptée ne veut pas dire en marche : quelles lois d'accélération du Canada servent vraiment

Since the US tariffs began in 2025, Canada's governments have passed a run of laws to approve resource and power projects faster. Of the seven fast-track laws we follow, three are switched on and used, one is in force but unused, one passed and is still switched off, one lapsed, and one is still before Parliament. The busiest is the narrowest: a BC law written around named power lines and wind farms. The broad powers to pick projects and set other laws aside sit unused almost everywhere.

Law Passed Switched on Used, to mid-October 2026
BC Bill 14 (power projects) May 2025 July 2025 Often: the Act's own list, then three regulations adding two lines and all land-based wind farms
BC Bill 31 (North Coast line ownership) November 2025 On passage Its framework underpins two orders made under another law; its own power not yet used
Federal Building Canada Act (Bill C-5) June 2025 On passage Once: one pipeline listed; the power to exempt projects from other federal laws unused
Ontario Special Economic Zones Act (Bill 5) June 2025 June 2025 Never: criteria set, no zone
BC Bill 15 (Infrastructure Projects Act) May 2025 No: one section only Never
Quebec Bill 5 No: lapsed August 2026 n/a n/a
Federal Bill C-39 Not yet: in committee n/a n/a

The narrow law is the busy one

BC's Bill 14 was in force 33 days after it passed, and has been widened three times since. The Renewable Energy Projects (Streamlined Permitting) Act (Renewable Energy Projects (Streamlined Permitting) Act (BC Bill 14) (Bill 14 (BC); SBC 2025, c. 12)) received Royal Assent on May 29, 2025 and took effect on July 1.1 The Act itself takes the North Coast Transmission Line (BC) and the nine wind projects BC Hydro picked in its 2024 call for power out of environmental assessment.2

Event · 2025-07-01 · action · CA-BCBC's Bill 14 comes into force, exempting the North Coast Transmission Line from the Environmental Assessment Act

British Columbia's Renewable Energy Projects (Streamlined Permitting) Act (Bill 14, SBC 2025, c. 12), which received royal assent on 29 May 2025, was brought into force on 1 July 2025 by B.C. Reg. 92/2025, according to BC Laws' table of legislative changes. Section 14 of the Act states that "The Environmental Assessment Act does not apply in relation to the following streamlined projects," listing selected wind energy projects, the North Coast Transmission Line project, and other prescribed wind and transmission line projects in the northwest, including lines from around Terrace.

Three regulations have widened that exemption: on July 1, 2025, to a line north of Terrace; in December 2025, to every land-based wind project; in July 2026, to a line serving the Ksi Lisims LNG site in the Nass Valley.34

Event · 2025-07-01 · action · CA-BCBC's first regulation under Bill 14 exempts the North of Terrace transmission line from environmental assessment

The Renewable Energy Projects (Streamlined Permitting) Regulation, B.C. Reg. 93/2025 (O.C. 321/2025), deposited on 27 June 2025 and effective 1 July 2025, the day Bill 14 came into force, prescribed two more transmission lines as streamlined projects: the North Montney line (from around the Site C dam) and the North of Terrace line (Terrace to around Bob Quinn Lake). It also made the North of Terrace line exempt from the Environmental Assessment Act under section 14(d) of the Act, according to BC Laws' point-in-time record of the regulation. This was the first use of Bill 14's power to add projects by regulation; the North Coast Transmission Line and BC Hydro's nine 2024 wind projects were exempted by the Act itself.

Event · 2025-12-15 · action · CA-BCBC exempts all land-based wind projects from environmental assessment under Bill 14 (B.C. Reg. 237/2025)

B.C. Reg. 237/2025, effective 15 December 2025, amended the Renewable Energy Projects (Streamlined Permitting) Regulation so that all land-based wind energy projects are prescribed for section 14(c) of Bill 14, which means the Environmental Assessment Act does not apply to them. It also put wind and solar projects over 5 MW under the BC Energy Regulator's fullest streamlining (level 3), required the regulator to give First Nations a chance to share Indigenous knowledge on those projects, and required a treaty nation's consent for wind projects that would formerly have needed an assessment when they sit on its treaty lands. Second regulatory use of Bill 14, according to BC Laws.

Event · 2026-07-10 · action · CA-BCBC exempts the Nass Valley transmission line to Ksi Lisims LNG from environmental assessment under Bill 14 (B.C. Reg. 122/2026)

B.C. Reg. 122/2026, effective 10 July 2026, added the Nass Valley Transmission Line project, a line from around the proposed Ksi Lisims LNG facility to the North of Terrace line, to the streamlined projects under Bill 14 and prescribed it for section 14(d), so the Environmental Assessment Act does not apply to it, according to BC Laws. This came eight days after Canada and BC signed the Cooperative Prosperity Agreement naming Ksi Lisims a priority project. Third regulatory use of Bill 14.

The result is on the ground. Construction of the North Coast line began on September 3, 2026.

Event · 2026-09-03 · action · CA-BCConstruction begins on BC Hydro's North Coast Transmission Line from Prince George toward Terrace

Premier David Eby, federal Energy Minister Tim Hodgson and BC Hydro marked the start of construction on the North Coast Transmission Line in Prince George on 3 September 2026. BC Hydro says the line will more than double the electricity that can be sent from Prince George to Terrace and beyond, for LNG plants, mines and other projects in northwest BC. The Terrace Standard reported that the province estimates the first two phases at roughly $6 billion, with phase 1 (Prince George to Glenannan) due by 2030 and phase 2 reaching Terrace by 2032; the Prime Minister's Office said in July 2026 that Ottawa will provide $3.9 billion, through various tools, toward the capital costs of phases 1 and 2; The Narwhal reported in October 2025 that the estimate had risen from about $3 billion in 2023. BC's Bill 14 exempted the line from environmental assessment, and a December 2025 provincial regulation exempted phases 1 and 2 from needing a certificate from the BC Utilities Commission. BC Hydro's procurement page lists right-of-way clearing contracts for two segments awarded to Duz Cho Construction LP in June and July 2026; the main line-construction contract for the first phase is to be awarded in May 2027, and the schedule for the contracts toward Terrace is under review. Lheidli T'enneh Chief Dolleen Logan told CBC News that five First Nations had issued a non-opposition letter pending a final agreement.

Bill 31 is in force too, but the order usually credited to it was made under another law. Bill 31 (Energy Statutes Amendment Act, 2025 (BC Bill 31) (Bill 31 (BC); SBC 2025, c. 23)) took effect on Royal Assent on November 27, 2025. It lets cabinet designate agreements under which BC Hydro and First Nations co-own parts of the North Coast line.5

Event · 2025-11-27 · action · CA-BCBC Bill 31 receives Royal Assent

BC's Bill 31, the Energy Statutes Amendment Act, received Royal Assent on 27 November 2025. It created the framework for First Nations co-ownership of the North Coast Transmission Line. The ministerial order of 8 December 2025 that exempted BC Hydro from needing a certificate of public convenience and necessity for the line was made under the Utilities Commission Act (B.C. Reg. 228/2025) and relies on that framework (Government of British Columbia; The Narwhal; BC Laws).

On December 8, the minister exempted the line's first two phases from needing a Utilities Commission certificate. That order cites section 22 of the Utilities Commission Act, not Bill 31; it relies on Bill 31's co-ownership framework.6 We found no designated co-ownership agreement yet.

Event · 2025-12-08 · action · CA-BCBC ministerial order exempts BC Hydro from the Utilities Commission certificate (CPCN) for the NCTL

On 8 December 2025 BC's Minister of Energy and Climate Solutions issued an order under the Utilities Commission Act (B.C. Reg. 228/2025, made under section 22) exempting BC Hydro from obtaining a certificate of public convenience and necessity from the BC Utilities Commission for the North Coast Transmission Line, to speed up construction (Government of British Columbia; BC Laws); the order relies on Bill 31's new framework for First Nations co-ownership of the line.

Ottawa: one listing, no exemptions

The Building Canada Act has been used once, to list a project, and its strongest power not at all. The Act, Part 2 of Bill C-5 (One Canadian Economy Act (incl. Building Canada Act) (C-5)), took effect on Royal Assent on June 26, 2025.7

Event · 2025-06-26 · action · CABill C-5, the One Canadian Economy Act, including the Building Canada Act for national-interest projects, receives Royal Assent

Bill C-5, the One Canadian Economy Act, received Royal Assent on 26 June 2025, less than three weeks after it was introduced on 6 June. It enacted two laws: the Free Trade and Labour Mobility in Canada Act, which removes federal barriers to trade and labour mobility between provinces, and the Building Canada Act, which came into force the same day. The Building Canada Act lets cabinet list projects it considers in the national interest; for those projects, the findings needed for federal approvals are deemed to be made in the project's favour, the minister can issue a single document that stands for the specified federal authorizations, and cabinet can by regulation exempt them from provisions of the federal laws listed in the Act. The government said a new Major Projects Office would lead the work.

On October 1, 2026, cabinet listed the Pacific Link (West Coast oil pipeline) as a national interest project, the first and so far the only one; the order was published on October 10.8 Listing treats a project as approved in principle; its conditions are still to be set.

Event · 2026-10-01 · action · CACarney lists the West Coast oil pipeline, renamed Pacific Link, as the first project of national interest under Schedule 1 of the Building Canada Act

In Fort McMurray on 1 October 2026, Prime Minister Carney listed the West Coast oil pipeline, now called Pacific Link, as a project of national interest under Schedule 1 of the Building Canada Act, the first project designated this way (CBC). The pipeline would carry about one million barrels a day roughly 1,250 km from Bruderheim, Alberta, to a deepwater port outside Delta, BC (Global News), on a southern route that the government says protects BC's North Coast and the Great Bear Sea. Canada and Alberta are to hold equal shares, Pembina Pipeline is the private investor and Trans Mountain Corporation leads development; Indigenous communities will be offered at least 10% ownership, financed through loan guarantees. The Major Projects Office is to finalize the conditions by 1 September 2027 (Prime Minister's Office). No final investment decision or in-service date was announced.

The Act also lets cabinet exempt listed projects from provisions of other federal laws.7 That power is unused: the federal orders database shows only two orders under the Act, the Pacific Link listing and one naming the minister in charge.9 Other projects are in the listing process.

Event · 2026-06-24 · document · CAOttawa starts the Building Canada Act listing process for Grays Bay Road and Port, the Mackenzie Valley Highway and the Deep Geological Repository

On 24 June 2026 Ottawa began the process to list three projects under the Building Canada Act: the Mackenzie Valley Highway, the Grays Bay Road and Port, and the Nuclear Waste Management Organization's deep geological repository. Listing 'would provide confidence that key federal permits and authorizations for the project will be granted'; consultations were to start in the following weeks, with decisions targeted for fall 2026 (Government of Canada). As of late September 2026 no project had been added to the Act's schedule.

Its follow-up is not law. Bill C-39 (Building Canada Strong Act (C-39)), built around one federal decision within a year, passed second reading 296 to 26 on October 8 and is in committee.10

Event · 2026-10-08 · action · CABill C-39 passes second reading in the House 296-26 with Conservative support and goes to a legislative committee; clause-by-clause set for mid-November

The House of Commons passed Bill C-39 (Building Canada Strong Act) at second reading on 2026-10-08, vote 178, 296 yeas to 26 nays with 10 paired (LEGISinfo), and referred it to the Legislative Committee on Bill C-39. Conservatives voted with the Liberals to send it to committee; Poilievre called it 'weak, watered-down, long-delayed' and said his party would propose amendments. The NDP and Greens opposed. On 2026-10-09 the committee adopted a motion to begin clause-by-clause consideration in mid-November and invited ministers MacKinnon, Dabrusin, Hajdu and LeBlanc (Canadian Press). Not yet passed by the House; Senate stages and Royal Assent still ahead.

Ontario: a zones law with no zones

Ontario's Special Economic Zones Act has been in force since June 5, 2025, and has never been used. Enacted by Bill 5 (Protect Ontario by Unleashing our Economy Act (Bill 5 (ON))), it lets cabinet designate zones by regulation and exempt "trusted proponents" and projects in them from provincial laws and municipal by-laws.11 The only regulation made under it, in force since January 1, 2026, sets the criteria; no zone, proponent or project has been designated.12

Event · 2025-12-16 · action · CA-ONOntario sets the criteria for special economic zones (O. Reg. 373/25); no zone designated by mid-October 2026

Ontario filed O. Reg. 373/25 under the Special Economic Zones Act, 2025 on 16 December 2025, in force on 1 January 2026. It sets the criteria cabinet and the minister must apply before designating a special economic zone, a trusted proponent or a designated project. The Act itself has been in force since 5 June 2025, but every designation and exemption under it must be made by regulation, and on e-Laws (currency date 14 October 2026) O. Reg. 373/25 is the only regulation made under the Act: no zone, trusted proponent or project had been designated, including the Billy Bishop airport zone the province announced in March 2026.

In May 2026 the province said it would soon designate Toronto's Billy Bishop airport. It hasn't. Other parts of Bill 5 did act directly: the law itself exempted a waste site at Dresden from environmental assessment.13

Event · 2026-05-28 · action · CA-ONOntario's Billy Bishop airport land-takeover law passes; province says it 'will soon designate' the airport a special economic zone

Ontario passed a law on 28 May 2026 allowing it to take over the Toronto Islands land where Billy Bishop Toronto City Airport sits, and Transportation Minister Prabmeet Sarkaria said the province would designate the airport a special economic zone to speed up its expansion (CP24; Global News). No designation had been made as of late September 2026.

BC's Bill 15: passed, still switched off

BC's broad fast-track law has been on the books for 17 months with its powers off. The Infrastructure Projects Act (Infrastructure Projects Act (Bill 15 (BC))) lets cabinet designate "provincially significant" projects, put their permits first, order approvals and override local planning rules. It received Royal Assent with Bill 14, after both passed on the Speaker's casting vote.

Event · 2025-05-29 · action · CA-BCBC's Infrastructure Projects Act (Bill 15) receives Royal Assent: broad fast-tracking powers that are almost entirely not yet in force

British Columbia's Infrastructure Projects Act (Bill 15) received Royal Assent on 29 May 2025. As passed, it lets cabinet designate "provincially significant" infrastructure projects and then speed them up: prioritized provincial permits, ministerial orders to issue approvals for projects that already hold an environmental assessment certificate, exemptions from local planning rules at a local authority's request, and orders replacing "constraints" that hold a project up. Apart from section 2 (the minister's general powers over infrastructure projects), its provisions come into force only by regulation, and none had been brought into force as of 22 September 2026, according to BC Laws. The province said pipelines and LNG facilities would be excluded from the provincially significant category, MLT Aikins reported. The environmental-assessment exemption for the North Coast Transmission Line is in a separate law passed the same day, Bill 14 (Renewable Energy Projects (Streamlined Permitting) Act), not in Bill 15.

Only section 2, the minister's general powers, took effect. Sections 1 and 3 to 47, which hold the designation and fast-track powers, wait for a cabinet regulation: BC Laws, current to October 13, 2026, still lists them as coming into force "by reg".14 The only cabinet order under the Act assigns it to a minister.15

The groundwork was done, then stopped. The province ran three consultations on the regulations; the last, on a faster environmental assessment for designated projects, closed on April 13, 2026.16 Nothing followed before the election was called in September.

Event · 2026-04-13 · document · CA-BCBC closes the last of three consultations on Bill 15's fast-track tools; the powers are still not in force when the election is called

BC's Ministry of Infrastructure ran three engagement phases on the regulations that would let the Infrastructure Projects Act (Bill 15) work: provincially significant projects (7 July to 30 September 2025), a qualified-professional reliance model for permits (21 July to 28 November 2025) and, led by the Environmental Assessment Office, an expedited environmental assessment for designated projects (10 March to 13 April 2026), according to the government's engagement page. No regulation or commencement order followed: BC Laws' table of legislative changes, current to 13 October 2026, still lists sections 1 and 3 to 47 as not in force ('by reg'), and the BC Laws order-in-council index shows only OIC 290/2025, which assigns the Act to a minister.

Quebec: never passed

Quebec's Bill 5 would have let cabinet set aside parts of other laws for "priority projects of national scope"; it never passed. Tabled in December 2025 (Bill 5 (QC): Act to speed up authorizations for priority projects of national scope), it stalled in committee in June and lapsed when the National Assembly was dissolved on August 27, 2026.1718

Event · 2026-08-27 · action · CA-QCQuebec Bill 5 lapses when the National Assembly is dissolved for the election, after stalling in committee in June

Clause-by-clause study in the Commission des finances publiques last sat on 2026-06-09 and adjourned while debating clause 32. On 2026-06-10 the Centre québécois du droit de l'environnement welcomed the bill's 'mort au feuilleton' (death on the order paper). On 2026-06-11 a Liberal MNA told the Assembly that Bill 5 (known as 'Q-5') had stopped advancing and was 'mort au feuilleton', and that its REM provisions had been moved into Bill 22. The Assembly adjourned sine die on 2026-06-12 without passing it. Formally the bill stayed on the order paper until the Assembly was dissolved on 2026-08-27 for the 2026-10-05 election, which ended it. (It had already survived the prorogation of 2026-04-08 and was reinstated at the same stage on 2026-05-06.) On 2026-09-09 the CAQ pledged, if re-elected, to table a new bill 'inspired by Q5'.

The Parti Québécois, which won on October 5, had listed no fast-track law among its priorities for its first 100 days, only a secretariat for regulatory relief.19 (On the campaign, see Quebec votes.)

Event · 2026-10-03 · statement · CA-QCPQ's 100-day priorities: a pay-freeze bill first and a secretariat for regulatory relief; no fast-track permitting law listed

Two days before the vote, the Parti Québécois published the first measures of a St-Pierre Plamondon government: a first bill freezing the pay of MNAs, ministers and the heads of the main Crown corporations until the budget is balanced; an emergency homelessness budget; removing tax on used goods; a fuel-tax cut worth 7 cents a litre; $100 million a year for food aid; a Secretariat for government efficiency and regulatory relief with a line-by-line review of programs and regulations and an audit of IT projects; lower immigration levels; and an Estates General on education in winter 2027 (Parti Québécois, 2026-10-03). The list does not mention reintroducing a fast-track permitting law like the CAQ's Bill 5, Churchill Falls or the referendum.

Who pays

Where the powers are used, the costs land on specific people. Bill 14 takes the North Coast line and BC's wind farms out of environmental assessment, the forum where First Nations, neighbours and others test a project before approval. The December 2025 wind regulation gives some of that back: First Nations get a chance to share Indigenous knowledge with the energy regulator, and wind projects on a treaty nation's lands need its consent.4

BC Hydro's customers carry the line. A December 2025 cabinet direction bars the Utilities Commission from refusing, for any reason, to let BC Hydro recover the line's costs in its rates, spread across its customers by the same percentage.20 Ottawa has promised C$3.9 billion toward the first two phases.21 Who wins: the LNG plants, mines and towns of the northwest that need the power, sooner.

BC after the vote

The Conservatives' win on October 24 hands Bill 15's switch to a party that voted against the law. On Elections BC's preliminary count, the Conservatives lead in 63 of 93 districts with 48% of the vote; the final count ends November 6.22 Switching Bill 15 on still takes only a cabinet order. But the party's MLAs voted against it in May 2025, and its platform does not mention it. The platform promises a law of its own instead: "one project, one review" approvals with fixed timelines.23

Event · 2026-10-24 · action · CA-BCBritish Columbia general election: the Conservatives win, leading in 63 of 93 districts on the preliminary count

On 24 October 2026 British Columbia elected a Conservative government. On Elections BC's preliminary count (as of 25 October, 99.96% of ballot boxes reporting), the Conservative Party led in 63 of 93 electoral districts with 48.05% of the vote, the BC NDP in 28 with 37.37% and the BC Greens in 2 with 10.97%; preliminary turnout was 48.12%. Mail-in and absentee ballots are counted in the final count, which ends on 6 November 2026. At the start of the campaign, 15% of respondents to an Angus Reid Institute survey (22 to 24 September) named US tariffs, Donald Trump or the alcohol ban among their top issues, far behind the cost of living (59%) and health care (42%).

Event · 2026-10-16 · document · CA-BCBC Conservative platform promises to legislate 'one project, one review' permitting with fixed timelines; it does not mention Bill 15

The Conservative Party of BC's 2026 platform, 'Lorne Doerkson's Plan for a Stronger BC' (file dated 16 October 2026), promises to 'Legislate permitting and approval certainty, with fixed timelines, "one project, one review" approvals, and quarterly reporting of progress on each project' (page 20) and to make BC 'the fastest place in North America to permit a mine and an LNG facility' (page 16). The platform does not mention Bill 15 (the Infrastructure Projects Act), which the party's MLAs voted against in May 2025, so it does not say whether a Conservative government would bring Bill 15 into force, amend it or repeal it.

Consent is the harder question. The platform also promises to "Repeal DRIPA", BC's law on the UN Declaration on the Rights of Indigenous Peoples (Declaration on the Rights of Indigenous Peoples Act (BC) (SBC 2019, c. 44 (Bill 41, 2019))).23 In the October 14 debate, interim leader Lorne Doerkson said: "The reality is that DRIPA has to be repealed."24 Repeal would not touch section 35 of the Constitution, which protects Aboriginal and treaty rights; the platform says it would "Restore the section 35 constitutional framework."

Event · 2026-10-14 · statement · CA-BCBC leaders' debate: Doerkson says DRIPA 'has to be repealed', Lowan says implement it, Eby does not restate his plan to amend it

In the televised leaders' debate in Vancouver on 14 October 2026, Conservative interim leader Lorne Doerkson said 'The reality is that DRIPA has to be repealed'. Green Leader Emily Lowan said her party 'must do the work of implementing DRIPA' and that 'DRIPA has no bearing on private property'. NDP Leader David Eby, who had vowed in the spring to amend DRIPA, did not reaffirm that commitment in the debate, CBC News reported; he said 'there is only one path forward and that is in partnership with the Indigenous people of this province' and 'we can't afford to have these major projects tied up in the courts'.

Our test runs to October 24, 2027: a hit needs a cabinet order switching on sections 1 and 3 to 47, and a project designated under them counts as use. An earlier marker: the Canada–BC agreement's first deliverables are due December 1. A second test watches for fast-track powers the winner left out of its platform.

Pre-registered prediction P8 · open · registered 2026-09-27BC Bill 15 switched on within 12 months of the 2026-10-24 election

Window: 2026-10-24 to 2027-10-24. What counts: The question: within 12 months of the BC election of 24 October 2026 (that is, by 24 October 2027), are the fast-track powers in BC's Bill 15 (sections 1 and 3 to 47) switched on, and are they used? If a Conservative government wins, we record whether it switches Bill 15 on, amends it or repeals it. What counts as a hit: a cabinet order (an order in council) brings sections 1 and 3 to 47 into force by 24 October …

Event · 2026-12-01 · document · CA-BCCanada–BC Cooperative Prosperity Agreement: Annex A deadline for the first set of deliverables

Annex A of the Canada–British Columbia Cooperative Prosperity Agreement (2 July 2026) sets 1 December 2026 as the date by which the first deliverables are due, including softwood lumber, steel, carbon-price matters, Trans Mountain revenue sharing, 'financial commitments related to a potential new pipeline to Asian markets', LNG support, coastal protection, child care, northwest protected areas, flood mitigation, and detailed funding for the Massey Tunnel replacement and the North Coast Transmission Line. These are implementation timelines, not payment dates (Prime Minister's Office backgrounder).

Documented by

What it means

The powers in use are narrow and named; the broad ones sit idle. Bill 14 names its projects, and the Building Canada Act's one use names one pipeline. The tools that would let a cabinet choose projects as it goes and set other laws aside (Bill 15, Ontario's zones, the federal exemption power, Quebec's Bill 5) are unused or dead. Seven laws are too few for a rule, but the pattern holds in all four governments.

Claim · mechanismA law passed is not a power switched on. BC's narrow Bill 14 was in force in 33 days and has been used repeatedly: the Act itself exempts the North Coast Transmission Line and nine wind projects from environmental assessment, and three regulations since July 2025 have extended the exemption to two more transmission lines and to all land-based wind projects. Bill 15's designation and fast-track powers (sections 1 and 3 to 47) were still not in force in mid-October 2026, more than 16 months after it passed; Quebec's Bill 5 lapsed; Ontario has not designated any special economic zone; and Ottawa has listed one national interest project without yet using its power to exempt projects from other federal laws. So the test of whether the build-out is locked in must ask whether powers are brought into force and used.
A law passed is not a power switched on. BC's narrow Bill 14 was in force in 33 days and has been used repeatedly: the Act itself exempts the North Coast Transmission Line and nine wind projects from environmental assessment, and three regulations since July 2025 have extended the exemption to two more transmission lines and to all land-based wind projects. Bill 15's designation and fast-track powers (sections 1 and 3 to 47) were still not in force in mid-October 2026, more than 16 months after it passed; Quebec's Bill 5 lapsed; Ontario has not designated any special economic zone; and Ottawa has listed one national interest project without yet using its power to exempt projects from other federal laws. So the test of whether the build-out is locked in must ask whether powers are brought into force and used.

So count use, not passage. A power that is used leaves things a later government would have to undo: the North Coast line is being built. A power on paper can be left off, rewritten or repealed by the next cabinet at little cost. (Hard to reverse is what we mean by "locked in" here, not the locked-in US supply terms that our forecast counts.)

What would change this: a cabinet order switching on Bill 15, Ontario's first zone, or Ottawa's first exemption regulation. We will record each when it comes.

Sources

  1. BC Laws, “Renewable Energy Projects (Streamlined Permitting) Act: Table of Legislative Changes”. ↩
  2. BC Laws, “Renewable Energy Projects (Streamlined Permitting) Act, SBC 2025, c. 12 (consolidated)”. ↩
  3. BC Laws, “Renewable Energy Projects (Streamlined Permitting) Regulation: Point in Time (amendments by B.C. Regs 237/2025 and 122/2026)”. ↩
  4. BC Laws, “Renewable Energy Projects (Streamlined Permitting) Regulation, B.C. Reg. 93/2025 (O.C. 321/2025), consolidated to 13 October 2026”, 2025-06-27. ↩ ↩
  5. Legislative Assembly of British Columbia (BC Laws), “Bill 31 – 2025: Energy Statutes Amendment Act, 2025 (first reading)”, 2025. ↩
  6. BC Laws (King's Printer), “North Coast Transmission Line Project Exemption Regulation (B.C. Reg. 228/2025)”, 2025-12-08. ↩
  7. Justice Laws (Canada), “Building Canada Act (S.C. 2025, c. 2, s. 5), full text”. ↩ ↩
  8. Canada Gazette, “Order Amending Schedule 1 to the Building Canada Act, P.C. 2026-925 (Canada Gazette, Part I, Vol. 160, No. 41)”, 2026-10-10. ↩
  9. Privy Council Office, “Orders in Council database: search by Act 'Building Canada Act', from 2025-06-26 (2 results)”, 2026-10-19. ↩
  10. Parliament of Canada (LEGISinfo), “LEGISinfo: C-39 (45-1), An Act respecting certain measures to strengthen the economy (Building Canada Strong Act)”, 2026-09. ↩
  11. Ontario e-Laws, “Special Economic Zones Act, 2025, S.O. 2025, c. 4, Sched. 9 (e-Laws, currency date 14 October 2026)”, 2025-06-05. ↩
  12. Ontario e-Laws, “O. Reg. 373/25: Criteria for Designations (Special Economic Zones Act, 2025)”, 2025-12-16. ↩
  13. Environmental Registry of Ontario, “ERO notice 025-0389 (York1 Dresden waste site)”. ↩
  14. BC Laws, “Infrastructure Projects Act, SBC 2025, c. 13: Table of Legislative Changes (current to 13 October 2026)”. ↩
  15. BC Laws, “BC Laws Orders in Council full-text search: "Infrastructure Projects Act" (1 hit, OIC 290/2025)”, 2026-10-19. ↩
  16. Government of British Columbia, “Infrastructure Projects Act - govTogetherBC (engagement July 7, 2025 to April 13, 2026)”. ↩
  17. Assemblée nationale du Québec, “Assemblée nationale: Projet de loi n° 5 (43-2)”. ↩
  18. Centre québécois du droit de l'environnement, “Mort au feuilleton du projet de loi 5 : un dénouement nécessaire dans l'intérêt public”, 2026-06-10. ↩
  19. Parti Québécois, “Paul St-Pierre Plamondon présente ses priorités pour les 100 premiers jours d'un gouvernement du Parti Québécois”, 2026-10-03. ↩
  20. Province of British Columbia, “OIC 561/2025: Direction to the British Columbia Utilities Commission Respecting the North Coast Transmission Line Project”, 2025-12-08. ↩
  21. Prime Minister's Office, “Canada and British Columbia strike new cooperative prosperity partnership to build a stronger, more sustainable economy”, 2026-07-02. ↩
  22. Elections BC, “2026 Provincial General Election: Results by Party (initial count, preliminary)”, 2026-10-25. ↩
  23. Conservative Party of BC, “Lorne Doerkson's Plan for a Stronger BC (Conservative Party of BC platform 2026)”, 2026-10-16. ↩ ↩
  24. CBC News, “B.C. party leaders lay out their plans for DRIPA in debate”, 2026-10-15. ↩

Changes since publication

A correction fixes something that was wrong. An update records the world moving: odds revised, a prediction settled, data refreshed. Newest first.

The charts, odds tables and other records embedded in this article always show the current data, so some figures may differ from the day it was published. This list records what changed since then.

  1. UpdatePacific Link (West Coast oil pipeline)

    Summary
    Summary fr

    Why: Added the Federal Court challenges to the listing and Pembina's description of its participation. Evidence: the Federal Court's online court records (16 applications for judicial review of the 1 October 2026 listing order, filed from 8 October to 2 November 2026, and the court's case management orders), Canadian Lawyer (3 November 2026) and CBC News (6 November 2026) on the grounds, and Pembina's third-quarter 2026 report and news release (5 November 2026).

    In the corrections log: Pacific Link (West Coast oil pipeline), 6 November 2026

  2. CorrectionBritish Columbia general election: the Conservatives win, leading in 63 of 93 districts on the preliminary count

    Summary
    Summary fr

    Why: The summary again gives the Angus Reid Institute campaign-start figure (survey of 22 to 24 September 2026: 15% named US tariffs, Donald Trump or the alcohol ban among their top issues, behind the cost of living at 59% and health care at 42%), which the result update had dropped although the survey remains a source of this event.

    In the corrections log: British Columbia general election: the Conservatives win, leading in 63 of 93 districts on the preliminary count, 30 October 2026