Construction begins on BC Hydro's North Coast Transmission Line from Prince George toward Terrace
Premier David Eby, federal Energy Minister Tim Hodgson and BC Hydro marked the start of construction on the North Coast Transmission Line in Prince George on 3 September 2026. BC Hydro says the line will more than double the electricity that can be sent from Prince George to Terrace and beyond, for LNG plants, mines and other projects in northwest BC. The Terrace Standard reported that the province estimates the first two phases at roughly $6 billion, with phase 1 (Prince George to Glenannan) due by 2030 and phase 2 reaching Terrace by 2032; the Prime Minister's Office said in July 2026 that Ottawa will provide $3.9 billion, through various tools, toward the capital costs of phases 1 and 2; The Narwhal reported in October 2025 that the estimate had risen from about $3 billion in 2023. BC's Bill 14 exempted the line from environmental assessment, and a December 2025 provincial regulation exempted phases 1 and 2 from needing a certificate from the BC Utilities Commission. BC Hydro's procurement page lists right-of-way clearing contracts for two segments awarded to Duz Cho Construction LP in June and July 2026; the main line-construction contract for the first phase is to be awarded in May 2027, and the schedule for the contracts toward Terrace is under review. Lheidli T'enneh Chief Dolleen Logan told CBC News that five First Nations had issued a non-opposition letter pending a final agreement.
- Date
- Kind
- Investment decision
- Where
- British Columbia
- Evidence
- Action: Something was done: a law switched on, a tariff imposed, money committed. How evidence is weighed
- Who
- Government of British Columbia (acted); BC Hydro (acted); Duz Cho Construction LP (counterparty)
Sources
- BC Hydro, “North Coast Transmission Line jobs and business opportunities” (external site). source record
- BC Laws, “Renewable Energy Projects (Streamlined Permitting) Act, SBC 2025, c. 12 (consolidated)” (external site). source record
- Legislative Assembly of British Columbia (BC Laws), “Bill 31 – 2025: Energy Statutes Amendment Act, 2025 (first reading)” (external site), . source record
- The Narwhal, “Bill 31: B.C. plans energy overhaul to court major projects” (external site), . source record
- BC Laws (King's Printer), “North Coast Transmission Line Project Exemption Regulation (B.C. Reg. 228/2025)” (external site), . source record
- Prime Minister's Office, “Canada and British Columbia strike new cooperative prosperity partnership to build a stronger, more sustainable economy” (external site), . source record
- Terrace Standard, “Work begins on B.C.'s North Coast Transmission Line” (external site), . source record
- CBC, “Construction starts on North Coast Transmission Line between Prince George and northwest B.C.” (external site), . source record
- BC Gov News (Office of the Premier), “North Coast Transmission Line breaking ground to power economic growth” (external site), . source record
Laws and agreements
- Renewable Energy Projects (Streamlined Permitting) Act (BC Bill 14) (Bill 14 (BC); SBC 2025, c. 12)
- Energy Statutes Amendment Act, 2025 (BC Bill 31) (Bill 31 (BC); SBC 2025, c. 23)
Projects
Claims that rest on this event
- A law passed is not a power switched on. BC's narrow Bill 14 was in force in 33 days and is being used for the North Coast Transmission Line, but only 1 of Bill 15's 48 sections was in force in late September 2026, 16 months after it passed, Quebec's Bill 5 lapsed, and Ontario has not yet designated any special economic zone. So the test of whether the build-out is locked in must ask whether powers are brought into force and used.
BC's Bill 14 exemption from environmental assessment is in use: the North Coast Transmission Line began construction on 3 September 2026.
How it bears on the outcome
| Explanation | Fit | Why |
|---|---|---|
| O0 No meaningful speed-up | Against weak | Construction starting on a roughly $6 billion line, with environmental and utility-commission exemptions, is consistent with a speed-up; only clearing contracts are let so far. |
| O1 Faster, but the extra output goes mostly elsewhere | Fits weak | The line serves LNG plants and mines on BC's north coast, whose exports go mainly overseas; consistent with extra output going elsewhere. |
| O2 Faster, and more volume reaches the US (this level or higher) | Neutral weak | Nothing here bears on volumes going to the US. |
| O3 Locked-in preferential terms for the US | Neutral weak | No US terms are involved. |
Corrections to this record
The federal contribution is now taken from the Prime Minister's Office release of 2 July 2026: $3.9 billion toward the capital costs of phases 1 and 2, replacing a $3.5 billion figure reported secondhand.
- Summary
- was
Premier David Eby, federal Energy Minister Tim Hodgson and BC Hydro marked the start of construction on the North Coast Transmission Line in Prince George on 3 September 2026. BC Hydro says the line will more than double the electricity that can be sent from Prince George to Terrace and beyond, for LNG plants, mines and other projects in northwest BC. The Terrace Standard reported that the province estimates the first two phases at roughly $6 billion, with phase 1 (Prince George to Glenannan) due by 2030 and phase 2 reaching Terrace by 2032, and that Ottawa has committed $3.5 billion; The Narwhal reported in October 2025 that the estimate had risen from about $3 billion in 2023. BC's Bill 14 exempted the line from environmental assessment, and a December 2025 provincial regulation exempted phases 1 and 2 from needing a certificate from the BC Utilities Commission. BC Hydro's procurement page lists right-of-way clearing contracts for two segments awarded to Duz Cho Construction LP in June and July 2026; the main line-construction contract for the first phase is to be awarded in May 2027, and the schedule for the contracts toward Terrace is under review. Lheidli T'enneh Chief Dolleen Logan told CBC News that five First Nations had issued a non-opposition letter pending a final agreement.nowPremier David Eby, federal Energy Minister Tim Hodgson and BC Hydro marked the start of construction on the North Coast Transmission Line in Prince George on 3 September 2026. BC Hydro says the line will more than double the electricity that can be sent from Prince George to Terrace and beyond, for LNG plants, mines and other projects in northwest BC. The Terrace Standard reported that the province estimates the first two phases at roughly $6 billion, with phase 1 (Prince George to Glenannan) due by 2030 and phase 2 reaching Terrace by 2032; the Prime Minister's Office said in July 2026 that Ottawa will provide $3.9 billion, through various tools, toward the capital costs of phases 1 and 2; The Narwhal reported in October 2025 that the estimate had risen from about $3 billion in 2023. BC's Bill 14 exempted the line from environmental assessment, and a December 2025 provincial regulation exempted phases 1 and 2 from needing a certificate from the BC Utilities Commission. BC Hydro's procurement page lists right-of-way clearing contracts for two segments awarded to Duz Cho Construction LP in June and July 2026; the main line-construction contract for the first phase is to be awarded in May 2027, and the schedule for the contracts toward Terrace is under review. Lheidli T'enneh Chief Dolleen Logan told CBC News that five First Nations had issued a non-opposition letter pending a final agreement. - Summary fr
- was
Le premier ministre David Eby, le ministre fédéral de l'Énergie Tim Hodgson et BC Hydro ont marqué le début de la construction de la ligne de transport North Coast (North Coast Transmission Line) à Prince George le 3 septembre 2026. Selon BC Hydro, la ligne fera plus que doubler la quantité d'électricité pouvant être acheminée de Prince George vers Terrace et au-delà, pour des usines de GNL, des mines et d'autres projets du nord-ouest de la Colombie-Britannique. Le Terrace Standard a rapporté que la province évalue les deux premières phases à environ 6 milliards de dollars, la phase 1 (de Prince George à Glenannan) devant être terminée d'ici 2030 et la phase 2 atteindre Terrace d'ici 2032, et qu'Ottawa s'est engagé à verser 3,5 milliards de dollars; The Narwhal a rapporté en octobre 2025 que l'estimation était passée d'environ 3 milliards de dollars en 2023. Le projet de loi 14 de la Colombie-Britannique a exempté la ligne d'évaluation environnementale, et un règlement provincial de décembre 2025 a dispensé les phases 1 et 2 de l'obligation d'obtenir un certificat de la BC Utilities Commission. La page d'approvisionnement de BC Hydro mentionne des contrats de déboisement de l'emprise pour deux tronçons attribués à Duz Cho Construction LP en juin et juillet 2026; le principal contrat de construction de la ligne pour la première phase doit être attribué en mai 2027, et le calendrier des contrats vers Terrace est en révision. La cheffe des Lheidli T'enneh, Dolleen Logan, a déclaré à CBC News que cinq Premières Nations avaient remis une lettre de non-opposition en attendant une entente définitive.nowLe premier ministre David Eby, le ministre fédéral de l'Énergie Tim Hodgson et BC Hydro ont marqué le début de la construction de la ligne de transport North Coast (North Coast Transmission Line) à Prince George le 3 septembre 2026. Selon BC Hydro, la ligne fera plus que doubler la quantité d'électricité pouvant être acheminée de Prince George vers Terrace et au-delà, pour des usines de GNL, des mines et d'autres projets du nord-ouest de la Colombie-Britannique. Le Terrace Standard a rapporté que la province évalue les deux premières phases à environ 6 milliards de dollars, la phase 1 (de Prince George à Glenannan) devant être terminée d'ici 2030 et la phase 2 atteindre Terrace d'ici 2032; le Cabinet du premier ministre a indiqué en juillet 2026 qu'Ottawa versera 3,9 milliards de dollars, au moyen de divers outils, pour les coûts en capital des phases 1 et 2; The Narwhal a rapporté en octobre 2025 que l'estimation était passée d'environ 3 milliards de dollars en 2023. Le projet de loi 14 de la Colombie-Britannique a exempté la ligne d'évaluation environnementale, et un règlement provincial de décembre 2025 a dispensé les phases 1 et 2 de l'obligation d'obtenir un certificat de la BC Utilities Commission. La page d'approvisionnement de BC Hydro mentionne des contrats de déboisement de l'emprise pour deux tronçons attribués à Duz Cho Construction LP en juin et juillet 2026; le principal contrat de construction de la ligne pour la première phase doit être attribué en mai 2027, et le calendrier des contrats vers Terrace est en révision. La cheffe des Lheidli T'enneh, Dolleen Logan, a déclaré à CBC News que cinq Premières Nations avaient remis une lettre de non-opposition en attendant une entente définitive.