ProjectElectricityGoes domestic
Churchill Falls upgrades / Gull Island
Upgrades to the existing Churchill Falls station in Labrador (about 1,275 MW) and a new Gull Island station (about 2,250 or 2,700 MW), to be held 60% by Newfoundland and Labrador Hydro and 40% by Hydro-Québec, under the mostly non-binding Definitive Cooperation and Implementation Agreement signed on 17 August 2026; new power contracts for the existing plant would run from 2027 to 2077. The parties aim to sign the final agreements by 31 December 2026, and the agreement ends on 31 March 2027 unless extended. Ottawa announced up to C$10 billion in federal financing and support. The power is mainly for Quebec's needs; no new line to the United States is part of the deal.
- Status
- Proposed
- Direction
- Domestic: Serves Canada itself.
- Capacity
- 3,975 MW
- Where
- Newfoundland and Labrador / Quebec
- Needs new laws?
- No: can proceed under existing rules
Owners
- Hydro-Québec (40%) as of 17 August 2026
Hydro-Québec, “Definitive Cooperation and Implementation Agreement (DCIA), Churchill Falls / Gull Island, 2026-08-17” (external site), . source record
- Newfoundland and Labrador Hydro (60%) as of 17 August 2026
Hydro-Québec, “Definitive Cooperation and Implementation Agreement (DCIA), Churchill Falls / Gull Island, 2026-08-17” (external site), . source record
Events
- Churchill Falls DCIA end of term, extendable by mutual agreement
- Target date for the Churchill Falls / Gull Island definitive agreements
- NL House of Assembly passes a resolution to proceed with the Churchill Falls deal, 21–18
- Innu Nation urges Newfoundland and Labrador MHAs to vote against the Churchill Falls deal
- St-Pierre Plamondon: a PQ government would not tear up the Churchill Falls deal if it is good, but would check every detail
- Labrador Trough corridor referred to the Major Projects Office
- Churchill Falls / Gull Island Definitive Cooperation and Implementation Agreement (DCIA) signed; mostly non-binding
- Newfoundland and Labrador Premier Wakeham drops his promised referendum on a Churchill Falls deal, citing federal involvement and US tariffs
- Ottawa announces up to $10 billion in federal financing and support for the Churchill Falls and Gull Island hydro package
- Quebec Innu (ITUM, Matimekush-Lac John): no Churchill Falls agreement without their consent
- NL names members of the Churchill Falls negotiation oversight committee
- Innu Nation postpones until further notice its second vote on the revised Hydro-Québec settlement
- NL releases the IRC report: the MOU 'is not in the overall best long-term interest' of the province
- Churchill Falls IRC delivers its report; the 2024 MOU expires the same day
- Newfoundland and Labrador launches an independent review of the 2024 Churchill Falls MOU (Huskilson, Holburn, Wilson)
- Newfoundland and Labrador election: Progressive Conservatives under Tony Wakeham win a majority, 21 of 40 seats
- First Innu Nation ratification vote on the Hydro-Québec settlement fails to reach the 50% turnout required
- Hydro-Québec and the Innu Nation sign a settlement MOU on the 2020 $4B claim
- Mike Wilson resigns from the Liberal-era Churchill Falls MOU review panel
- Hydro-Québec was a net buyer of about 3.4 TWh on outside markets in 2025, a third straight low-runoff year (a net seller of about 5.7 TWh in 2024)
- Hydro-Québec and NL Hydro sign a largely non-binding memorandum of understanding on Churchill Falls and Gull Island
- Innu Nation Grand Chief signs the 2024 Churchill Falls MOU and calls it historic
- NL Hydro's board approves a negotiating mandate for Gull Island
- Newfoundland and Labrador approves a mandate to negotiate a new Churchill Falls agreement with Hydro-Québec
- Innu Nation Grand Chief says grievances over past hydro projects must be addressed before more development on the Churchill River
- Innu Nation sues Hydro-Québec over the existing Churchill Falls plant, claiming $4B