- Europe is a real but small diversification channel, made of defence and resources. The binding items are Canada's agreement to join the EU's SAFE …
- None of the new export routes is tied to a refinery, upgrader, smelter or steel plant; only two container terminals (Roberts Bank Terminal 2 and Contrecoeur) …
Latest articles
No article cites this record yet.
Events it documents
- Rio Tinto slows construction of the Nemaska Lithium hydroxide plant at Bécancour for 2026; first production 2028
- Rio Tinto's AP60 expansion pours first hot metal (March 2026); the last Arvida potlines close in June 2026, leaving Quebec capacity roughly unchanged
- Alcoa and Rio Tinto redirect Canadian primary aluminum to customers outside the US after the 50% tariff