Carnet 49An independent journal, with its receipts
Français

ProjectElectricityGoes south

New England Clean Energy Connect (NECEC)

1,200 MW high-voltage direct-current line carrying Hydro-Québec power through Maine into the New England grid, under 20-year contracts with Massachusetts utilities for about 9.55 TWh a year. It entered commercial operation on January 16, 2026. Deliveries were interrupted several times in its first months, and in September 2026 the Massachusetts utilities and Hydro-Québec took a payment dispute over the shortfalls to court.

Status
In service
Direction
South: Carries Canadian output to the United States.
Capacity
1,200 MW
Where
Quebec
In service
16 January 2026
Needs new laws?
No: can proceed under existing rules

Articles that cite this record

Events