ProjectCritical mineralsGoes mixed
North American Lithium expansion, Stage 1 (Elevra)
Stage 1 of Elevra Lithium's staged brownfield expansion of the North American Lithium spodumene mine at La Corne, Quebec: raising the plant to its permitted 4,500 tonnes a day for a 15-20% increase in concentrate output from mid-2027, within existing permits (Stage 1 capital C$92 million). The whole staged expansion was fully funded in May 2026 (with C$145 million from the Canada Growth Fund), and execution began after a June 2026 groundbreaking, with long-lead equipment ordered (Elevra FY26 results; NAL expansion prefeasibility study, September 2026). Elevra owns NAL 100%.
- Status
- Under construction
- Direction
- Mixed: Can go more than one way.
- Where
- Quebec
- Investment decision
- May 2026
Owners
- Elevra Lithium (100%) as of 28 August 2026
Elevra Lithium, “Elevra Lithium FY26 Full Year Results (ASX announcement, Form 6-K exhibit 99.4)” (external site), . source record